Sunday 22 September 2013

Where we are at

Well we were off to a good start.
24 May – Plans approved.
10 July - Final docs signed and submitted – ready to go
25 July - Blocked scrapped
12 August - Slab poured
21 August - Drainage completed
26 August - Frames started
2 September - Frames completed
10 September - Plumbing completed
13 September -Brickwork completed lower floor
16 September - Scaffolding erected for second floor
Week 16 - 22 September - NOTHING happened bricks were supposed to be completed - NOT HAPPY